Project Timeline

September 2019

Project Kick off

January 2020

System Requirements Review (SRR) - DESY, Elop, IAI

March 2020

Camera System Design Review (SDR) - DESY

April 2020

Payload System Design Review (SDR) - Elop

May 2020

Spacecraft System Design Review (SDR) - IAI

October 2020

Payload Perliminary Design Review (PDR) - Elop

December 2020

Camera Perliminary Design Review (PDR) - DESY

February 2021

Spacecraft Perliminary Design Review (PDR) - IAI

October 2021

Camera Critical Desgin Review (CDR) - DESY

January 2022

Payload Critical Design Review (CDR) - Elop

April 2022

Spacecraft Critical Design Review (CDR) - IAI

We are here!

September 2022

Ground Control Segment Critical Design Review (GCS CDR) - IAI

March 2023

Supply of Camera - DESY

March 2024

Supply of Payload - Elop

August 2024

Science Operation Center (SOC) Readiness Review - WIS

September 2024

Readiness Review Ground Control  Segment - IAI

January 2025

ULTRASAT Delivery Review Board (DRB) - IAI

Q2 2025

launch